Mezzanine Floor, Creating Suite of Meeting Rooms/Offices within Factory Space

Saint Gobain were looking to provide for their employees a larger and better appointed suit of meeting rooms and offices within their factory space.

The solution was to demolish the existing single storey office and erect a new fire rated mezzanine floor providing double the amount of office space.

Saint Gobain appointed aci to act as main contractor for the works which were commenced within 7 days from order and completed with 6 weeks under strict CDM and health and safety control.

The timescales were very tight and weekend working was necessary to hit the promised completion date.

A special feature of the mezzanine design was a large cantilever section to allow visibility of the factory and production line whilst not impeding the working area below

Scope of Works

  • Project completed under strict CDM regulations in 6 weeks
  • Safe demolition of existing structure inc. asbestos removal
  • Accoustic partition walls
  • Partition Walls, Doors and Glass and Blinds
  • Steel partitioning with sliding doors
  • High frequency dimming light fittings
  • Factory barrier rails
  • Mezzanine Floor and Fire Rating
  • Office Furniture
  • Air Conditioning, Ventilation and Electrical Installation
  • Wall Coverings
  • Projectors and Screens
  • Vinyl and Carpeted Floor Coverings
Mezzanine Floor, Creating Suite of Meeting Rooms/Offices within Factory Space

What did the client think?

Thanks aci – Great job under very difficult conditions – thanks again!

Facilities Manager, Saint Gobain